Also known as Progressive Payment Scheme, allows you to service your loan via monthly instalments progressively stage by stage as the property is being built.
Stage Payment Under a Standard Payment Scheme (% of Purchase Price)
Upon the grant of Option to Purchase 5% (Booking Fee)
Upon signing of the Sale & Purchase Agreement or within 8 weeks from the Option date 20% less Booking Fee
Completion of foundation work 10%
Completion of reinforced concrete framework of unit 10%
Completion of partition walls of unit 5%
Completion of roofing/ceiling of unit 5%
Completion of door sub-frames/ door frames, window frames, electrical wiring, internal plastering and plumbing of unit 5%
Completion of car park, roads and drains serving the housing project 5%
Notice of Vacant Possession (TOP) 25%
On Completion date 15%
https://www.the-florenceresidences.com/wp-content/uploads/2021/03/output-onlinepngtools.png

Developer: Logan Property (Singapore) Company Pte. Limited
Tenure: 99 Years Leasehold
Site Area: 389,239 sqft
Total Units: 1,410
Expected TOP: March 2023
Expected CSC: March 2026

PROUDLY DEVELOPED BY

Sitemap | Disclaimer

Copyright © 2021 | The Florence Residences | Logan Property (Singapore) Company Pte. Limited | +65 6816-8866

error: Content is protected !!